Eric — Chip Off The Old BlockArborist. Tree clearing immediately post-settlement. Ecology + bushfire reports already permit removal.
Andrew Pine — Pine LawLawyer. Drafts connections easement off the new survey plan, ASAP.
Richard — Lateral CertificationBuilding approvals for all three houses (incl. dummy BA sets for 96/98).
Civil engineer (TBC)Civil design, easement sizing, runs the operational-works approval process.
Geotech engineer (TBC)Soil tests + rock-stabilisation check of contoured earth along the easement path.
Surveyor (TBC)Documents easement size on a new survey plan once civil feedback lands.
Ecology + bushfire consultantsReports already in hand (clearing approved). Updated reports needed for the 96/98 upsize stage.